Overview
The Covid pandemic placed immense strain on lessors and airlines alike. The recent case in the High Court of Peregrine Aviation Bravo v Laudamotion [2023] EWHC 48 (Comm) sheds some light on the impact the pandemic had on relationships between lessors and airlines, especially amidst the dystopian atmosphere of the early lockdowns, and highlights important issues to take into consideration when looking to terminate the leasing of (or the commitment to lease) an aircraft.
By way of brief overview:
- The claimant lessor, acting through various entities (including Peregrine Aviation Bravo) (hereinafter, the “Lessor”), had several existing leases with Laudamotion, a subsidiary of Ryanair (and hereinafter, the “Airline”), under which the aircraft had been delivered (the “Delivered Leases”), and had entered into four new leases for mid-life aircraft scheduled for delivery during Q2 2020 (the “New Leases”).
- Whilst the Delivered Leases were guaranteed by Ryanair, only one of the four New Leases was guaranteed by Ryanair (with the apparent intention that the other three New Leases would be guaranteed closer to delivery).
- As a consequence of the Covid pandemic which had spread widely across Europe by March 2020, there were extensive discussions and communications between the Lessor and the Airline in March and April 2020 concerning the status of the aircraft already operational under the Delivered Leases and the aircraft scheduled to be delivered under the New Leases.
- The Airline sent at times bold communications, two of which were later cited as grounds for an event of default. The first, sent on 18 March 2020, stated amongst things that delivery under the New Leases would be unilaterally deferred until at least the end of June 2020. The second, sent on 20 April 2020, indicated that it would apply a unilateral rent reduction to the Delivered Leases and that it could not accept delivery of the aircraft under the New Leases. It is important to note that the Airline did continue to pay rent (when due) in full under the Delivered Leases.
- The Lessor eventually decided to force delivery of the first aircraft, MSN 3361, as a “shot across the bow”, tendering it for delivery on 7 May 2020 having only given notice (in a best-case scenario) on 1 May 2020.
- The Airline claimed that, amongst other things, the aircraft was not in the requisite delivery condition and that inadequate notice had been provided. The Lessor terminated the first New Lease and the remaining three New Leases on 15 May 2020.
- The Lessor subsequently re-leased the aircraft to SmartLynx, an ACMI operator, on a power-by-the-hour arrangement.
Disputes arose between the parties which fell to be resolved in the High Court of England and Wales. Henshaw J, the case judge, found against the Lessor, deciding that the Airline did not wrongfully fail to take delivery as alleged by the Lessor and that no events of default had occurred. Ancillary claims against the guarantor also failed as a consequence.
Continue Reading High Court strikes a cautionary note on lease termination: The recent case of Peregrine v Laudamotion